Project managment
As a consultant you have been asked by the Global Retail Solutions Group (GRS) to develop an implementable project plan for a point of sale and stock control system for a proposed chain (DSE) of retail outlets across Australia. You have been supplied the following information, information not available maybe assumed, this will be a competitive bid targeting the dual goals of quick implementation and low cost.

DSE is an aggressive player in the growing DIY electronics market with a plan to open a chain of retail outlets to further their growth in the market. Outlets will be located in major cities in seven states. The larger cities will have more than one store. Critical to sales is monitoring sales and stock turn to ensure adequate stock is available when demanded. Each store will be responsible for day-to-day operations, however, there is a strong central management structure at the national level. The services provided by the organization include volume buying to gain discounts, pricing, merchandising strategies, and consolidation of performance reporting for the corporate management.

The Information Systems Department at DSE’s corporate office has been given the assignment to develop a transaction processing system that will apply modern RFID code scanning at the point of sale and provide automatic inventory control. The system will also relieve the store personnel of the tedious task of generating sales and performance reports as required by the head office.

An earlier project has successfully defined the store level hardware that will be used at the points of transaction plus the communications network that will connect the stores with the state offices. This hardware consists of standard PCs plus the scanning equipment and any other specialized interface hardware needed. The communications facility consists of a polled network and will be based on dial-up lines from the head office to the individual stores. The stores have no requirement to communicate with each other.

At this point in time, consider yourself a consultant who has to bid for the software development piece of the project upon which this system is based. You will have access to several DSE employees to execute the various tasks that your project proposal will guide to a successful conclusion.

You have selected Microsoft Project as a software tool to assist in the development of your proposal.

Five major activities have been defined, each of which contains a number of tasks. The tasks have been defined such that each task requires only one resource. Since there is a limit to the number of resources available to the project, a resource will probably be assigned several tasks throughout the duration of the project. However, for best efficiency the team has decided that it is best to schedule the completion of one task before the next task is started by the same resource. Your project design has divided the work into sufficiently small increments that this strategy can be successfully applied.

Since the software development is being done on standard platforms with standard operating environments and well-known development tools, there are no restrictions on the assignment of resources to tasks. This means that you can reassign tasks among your resource pool as required to make the most efficient schedule.

From the information supplied by DSE (below) you have to develop a design for the project. Your next task is to transfer the entire design to Microsoft Project so that you can clearly establish a timeline for the project based on detailed planning and costs associated with your preferred choice including resource utilisation. A concise business proposal including outputs from Microsoft Project will be required to make your case.
Transaction processor

User Interface – Driver code to display individual transaction data, including item name and price to both the customer and the operator. Richard – 3 days
Peripheral Interface – Driver code to accept input data from the UPC scanner, scale and keyboard. Richard – 2 days
Price Look-up – Inter-process communication to send item identification to the database and retrieve price information. Elizabeth – 3 days
Order Control – Application code to accumulate item totals, accepting multiple quantities and calculating total price. This module also assigns items by tax category and maintains a total for each tax rate. Elizabeth – 10 days
Payment Resolution – Application code to accept cash and debit transfers as payment for the order total. Note: Requires communications facilities with banking network. Harry – 4 days Transaction Resolution – Application code to update inventory, accumulate sales amounts, account for taxes collected by category. Harry – 5 days
Receipt Printing – Application and driver code to print itemized receipt for cash sales and authorization form for debit transactions. Richard – 4 days

Price and inventory file

Database Design – Schema design to include full description of each item and associated data to support price look-up and inventory management functions. Also includes tax rate by category and application of specific state tax rules. Sam – 5 days
Database Access Library – Library applications that accept queries from the transaction processor and return data requested by the transaction. Includes inventory adjustment based on sale quantities. Jenny – 12 days
Database Maintenance Library – Library applications that accept and apply price updates, add new items, change tax categories and update inventory status with new receipts. Ellie – 12 days
Database Report Generation – Library applications that support database search for specific input criteria for product movement studies etc. Sam – 10 days

Inventory management

Daily Status Report – Application code to search the database for all items that have been flagged as low stock status, sorted by supplier and displayed on a PC in the store manager’s office. Elizabeth – 5 days
Item History Report – An interactive query transaction to display on the manager’s terminal the sales pattern for a selected item over the last two months. Jenny – 4 days
Order Generation – Application code that accepts as input a specific item and returns the economic lot quantity and other pertinent vendor data. Also allow the manager to select and process an order to replenish stock. Harry – 7 days
Order Communication – Application code that collects the decisions made in the Order Generation process and prepares an order for transmission to the head office. Harry – 3 days
Receipt Processor – Application code that accepts input from the receiving dock via either scanner or keyboard to signal the receipt of stock. Richard – 3 days
Inventory Update – Application code access the database library to update quantities in stock after receipt of shipments. Richard – 5 days

Communications

Banking Network Interface – Driver code to initiate connection to local transaction switch and submit account and charge amount. Includes confirmation transaction and error recovery. Elizabeth – 7 days
State Network Interface – Driver code to control incoming calls from the head office on the dial-up network. Handles automatic answer, message transfer in block mode and error recovery. Harry – 12 days
Communications Command Interpreter – Application code to recognize incoming requests from the head office for various store performance reports. Jenny – 5 days
Report Generator – Applications code to respond to a request from the communications interface to generate specific reports and return data as a file for sending to the state office in block mode. Each report is saved at the store and may be sent during the same communications session as the request or in a later session. Ellie – 10 days

Documentation

Help for Transaction Processor – Richard – 5 days,
Help for Price and Inventory Modules – Jenny – 5 days
Help for Inventory Management – Harry – 5 days
Help for Communications – Ellie – 5 days

Alpha test

This test is conducted by a resource obtained from the head office. The objective is to verify that all of the functions are operational and that the results of each transaction are accurate and reliable. Barry – 20 days
Developer support is provided as follows: Richard – 5 days, Jenny – 7 days, Harry – 6 days, and Ellie – 5 days

Beta test

This test is to be conducted by actual users in several of the retail outlets. No development resources are allocated to this test. The duration of the test is 60 days.
Start roll-out

This milestone marks the completion of the project. The rate at which the product is actually installed and delivered to operating personnel depends on the availability of resources and plans from the individual stores. Each of these is the possible subject of a project plan.
Resource costs

$/hour $/hour
Richard 200 Elizabeth 100
Jenny 100 Ellie 90
Harry 100 Outside Contractors – Sam 200
Barry 100 Transfer pricing – other internal resources 120

Task A

You are required to present your project plan to the project sponsor that shows how you propose to implement this project. As a minimum you should provide your plan as a business report including typical plan components such as objectives and goals, risk assessment and other elements you feel are important to support this project, and required to obtain approval from the project sponsor.

You must also incorporate, as a minimum, the following specific project software outputs:

project summary
gantt chart
cash flow/budget
network diagram
resource sheet, and
any other content you feel is appropriate.
The assignment will be marked on the basis of the sponsor’s understanding of how you plan to complete this project in the most effective manner. This means value for money, timeframe, presentation, understanding of your approach and consistency and accuracy of the plan.

You are presenting your plan to the project sponsor who needs to understand your project plan, have confidence in you as the project manager and have the appropriate supporting documentation to back up your approach.

Task B

Generate a Turnitin originality report and submit this report via EASTS;

Answer the following questions to interpret the Turnitin originality report. The questions can be found through the following link: http://www.academicinternational.org/teaching/turnitin.pdf Submit your answers via EASTS.
Turnitin is more than a ‘gotcha’ device – it is an effective learning tool:

Because the sophisticated use of sources involves a complex set of research, critical thinking, and writing skills, you should expect to take several years to master them. Turnitin can be a helpful tool in this developmental process. You should use your originality reports as feedback on a first draft so that you can improve your use of sources before submitting the final draft for marking.

Interpreting the Turnitin Originality Report:

After you submit your draft to Turnitin for self-checking, you should look carefully at the originality report so that you can improve on your use of sources. Your essay will be on the left side of the screen, and the matching colour-coded sources will be listed on the right. Then you can make the necessary changes to your essay before you submit the final draft for marking.

You need to register with Turnitin to create a Student Account under the CSU Turnitin Licence at http://www.turnitin.com/login_page.asp

Further information on how to use Turnitin can be found through the following link: http://student.csu.edu.au/study/plagiarism/checking

Rationale
This assessment task covers topics 1 to 9 and has been designed to ensure that you are engaging with the subject content on a regular basis. More specifically it seeks to assess your ability to:

demonstrate how a practicing project manager actually applies project management skills, methods, techniques and tools ;
use an industry standard project management software tool (Microsoft Project);
apply project management skills, methods, techniques and tools to a real world problem typical of a project manager;

FOR YOUR ASSIGNMENTS TO BE DONE AT A CHEAPER PRICE PLACE THIS ORDER OR A SIMILAR ORDER WITH US NOW

Leave a Reply

WPMessenger